Programme period · 01 Jul 2026 – 30 Jun 2027 · 12 months
The Link South Africa
Section 7 · Programme Duration

12-month implementation roadmap

A phased delivery plan running from 01 July 2026 to 30 June 2027. Every phase below has a specific intent, a defined set of activities, sign-off gates and the verifiable evidence it produces — so 4Racing can audit progress at any week of the programme.

Programme duration
12 months
01 Jul 2026 – 30 Jun 2027
Delivery phases
5
Active delivery weeks
52
Steering reviews
4
Quarterly
Programme phase distribution (weeks)
2w
4w
2w
38w
6w
Inception & Mobilisation
Weeks 1–2 · 01 – 14 July 2026
Diagnostic Assessment
Weeks 3–6 · 15 July – 11 August 2026
Incubation Design
Weeks 7–8 · 12 – 25 August 2026
Implementation & Mentorship
Weeks 9–46 · 26 August 2026 – 17 May 2027 (≈ 9.5 months)
Close-out & Impact
Weeks 47–52 · 18 May – 30 June 2027
Bar widths represent the proportion of the 52-week programme allocated to each phase.
Effort intensity by phase (weeks)
Inception & Mobilisation2 wks
Weeks 1–2 · 01 – 14 July 2026
Diagnostic Assessment4 wks
Weeks 3–6 · 15 July – 11 August 2026
Incubation Design2 wks
Weeks 7–8 · 12 – 25 August 2026
Implementation & Mentorship38 wks
Weeks 9–46 · 26 August 2026 – 17 May 2027 (≈ 9.5 months)
Close-out & Impact6 wks
Weeks 47–52 · 18 May – 30 June 2027

Phase-by-phase detail

Each phase below describes the intent, the specific activities executed on the ground, and the outcomes that gate the move to the next phase.

1
Phase 1 — Inception & Mobilisation
Weeks 1–2 · 01 – 14 July 2026

We use the first two weeks to lock the operating rules of the programme before any field work begins. The Link convenes an inception meeting with 4Racing's appointed sponsor and contract manager, finalises the contracting pack (SLAs, POPIA & NDA), publishes the governance charter, and stands up the client portal that 4Racing will use for the next 12 months. Each beneficiary is formally onboarded, given portal credentials and walked through the data-collection protocols so Phase 2 can start without delay.

Activities
  • Inception meeting with 4Racing sponsor & contract manager
  • Signed contract pack, SLAs, POPIA & NDA in place
  • Stakeholder map, RACI and escalation paths published
  • Beneficiary onboarding pack issued (×4) and portal access granted
  • Risk register v1.0, decision log and change-control procedure opened
  • Reporting calendar (monthly + quarterly) communicated to all parties
Phase-exit outcomes
  • Signed Inception Plan, ratified by Steering Committee
  • Live client portal with all four beneficiaries onboarded
  • Single source of truth for governance, scope and cadence
2
Phase 2 — Diagnostic Assessment
Weeks 3–6 · 15 July – 11 August 2026

A 7-dimension diagnostic is conducted on-site at each enterprise: business model, financial sustainability, operations, market & sales pipeline, legal/tax/B-BBEE compliance, leadership capability and digital maturity. Two specialists per visit review 24 months of management accounts, walk the operations, interview the owner and staff, and audit the compliance file. Each enterprise receives a Diagnostic Report with a 1–5 maturity scorecard per dimension and a prioritised 90/180/365-day development roadmap.

Activities
  • On-site diagnostic visit per beneficiary (×4)
  • Financial scan: 24-month trend, ratio analysis, cash-flow review
  • Operations, quality and capacity walk-through
  • Compliance audit: SARS, CIPC, B-BBEE, sector-specific
  • Digital maturity scorecard and market/pipeline review
  • Counter-signed Diagnostic Report per beneficiary
Phase-exit outcomes
  • Verified, evidence-anchored baseline per enterprise
  • Maturity scorecard (×4) lodged in the portal
  • Prioritised development roadmaps ready for Phase 3 design
3
Phase 3 — Incubation Design
Weeks 7–8 · 12 – 25 August 2026

Each diagnostic is converted into a sequenced 10-month incubation plan with named owners, monthly milestones, evidence requirements and a measurable supplier-readiness end-state mapped to the 4Racing supply chain. Workstreams (skills, finance, compliance, market, digital) are scheduled against the beneficiary's capacity to absorb interventions; budget is allocated line-item per enterprise; the KPI framework is baselined; and the plans are signed by both the beneficiary and the 4Racing Working Group sponsor before any spend begins.

Activities
  • Tailored Incubation Plan per beneficiary (×4)
  • Monthly milestone calendar with owner & evidence per milestone
  • Workstream sequencing (skills, finance, compliance, market, digital)
  • Line-item budget allocation per beneficiary
  • KPI baseline sheet and supplier-readiness checklist
  • Steering Committee sign-off pack
Phase-exit outcomes
  • Four signed Incubation Plans on the portal
  • Locked baseline + KPI sheet ready for live tracking
  • Steering Committee approval to commence implementation
4
Phase 4 — Implementation & Mentorship
Weeks 9–46 · 26 August 2026 – 17 May 2027 (≈ 9.5 months)

The delivery engine of the programme. Across roughly 9.5 months we run ten monthly mentorship cycles, four structured training programmes (FIN-101 Finance, COMP-201 Compliance, MKT-301 Market Access, DIG-401 Digital), and on-the-ground interventions — system implementations, branding refreshes, compliance remediation, equipment readiness and direct supplier onboarding into the 4Racing supply chain. Every session is logged with attendance, outputs and beneficiary sign-off. 4Racing receives a monthly progress report and a quarterly steering review with KPI movement, RAG status, spend pacing and decisions required.

Activities
  • Ten monthly mentorship & coaching cycles (≥ 2 sessions / beneficiary / month)
  • FIN-101, COMP-201, MKT-301, DIG-401, GOV-501 programmes delivered
  • Direct interventions: systems, branding, equipment, compliance remediation
  • Buyer-matchmaking & supplier onboarding into the 4Racing supply chain
  • Monthly Progress Reports (×10) auto-published to the portal
  • Quarterly Steering Reviews — Q1 Sep 2026, Q2 Dec 2026, Q3 Mar 2027
Phase-exit outcomes
  • ≥ 90% session attendance across all beneficiaries
  • 100% of compliance gaps from Phase 2 closed
  • ≥ 2 qualified buyer opportunities per beneficiary
  • All four enterprises supplier-onboarding-ready
5
Phase 5 — Close-out & Impact
Weeks 47–52 · 18 May – 30 June 2027

We close the programme with a final on-site impact assessment per enterprise, lock the verification-ready evidence file, hand over all artefacts to 4Racing, and table a consolidated Programme Impact Report with verified KPI movement, supplier-onboarding outcomes, jobs sustained/created and a costed next-phase recommendation. An independent dry-run review is conducted on the evidence file before final verifier submission so that 4Racing's B-BBEE verification proceeds without further preparation.

Activities
  • Final on-site impact assessment per beneficiary (×4)
  • Independent dry-run review of the evidence file
  • Consolidated Programme Impact Report
  • Verifier-indexed Evidence File (digital + printable)
  • Handover of all artefacts and portal ownership to 4Racing
  • Costed next-phase recommendation
Phase-exit outcomes
  • First-time-pass-ready B-BBEE ESD evidence file
  • Signed Programme Impact Report on the Steering Committee minutes
  • Clean handover with no open actions

Headline milestones at a glance

DateMilestonePhase
07 Jul 2026Inception sign-offPhase 1
11 Aug 2026All 4 diagnostics completePhase 2
25 Aug 2026Incubation Plans signed offPhase 3
25 Sep 2026Q1 Steering CommitteePhase 4
18 Dec 2026Mid-programme impact snapshotPhase 4
27 Mar 2027Q3 Steering CommitteePhase 4
15 Jun 2027Final impact report & evidence filePhase 5
30 Jun 2027Programme close · 12-month term completePhase 5